Project
Cowal Gold Mine
Mining
Principal Client
Evolution Mining
Head Contractor
Global Soils
Location
West Wyalong, NSW
Duration
2 Days
scope of works
Global Soils was contracted to provide a long-term aerial dust suppression solution across both Tailings Storage Facilities – totalling 2,500,000m2. The scope of works included:
- Supply of Vital Bon-Matt Stonewall
- Planning and safety management of helicopter and hot refuelling operations
- Mine specified hydroseeding trucks to continually mix and dispatch product
- Skid steer & operator to fill hopper and load pallets onto the hydroseeders
- Helicopter completing 1 load (700L) every two minutes
- • Dust Control
Global Soils
Cowal Gold Mine
Global Soils was contracted to provide a long-term aerial dust suppression solution across both Tailings Storage Facilities – totalling 2,500,000m2. The scope of works included:
- Supply of Vital Bon-Matt Stonewall
- Planning and safety management of helicopter and hot refuelling operations
- Mine specified hydroseeding trucks to continually mix and dispatch product
- Skid steer & operator to fill hopper and load pallets onto the hydroseeders
- Helicopter completing 1 load (700L) every two minutes
See More Projects
Contact Us
Contact B&K Group Australia now via our contact form or directly through the below head office contact details:
- 02 4384 4159
- info@thebkgroup.com.au
- 6 Apprentice Dr, Berkeley Vale NSW 2261






